Today we poured concrete on the stadium seats and ramps in auditorium 1.
We have 10 days to open auditoriums 1 & 2. Matt my carpenter foreman & I
are working 12 hours a day 7 days a week TO MAKE THIS HAPPEN.
Tuesday, March 23, 2010
Saturday, March 20, 2010
COLUMBUS WEEK 1
We are now working on a 10 screen renovation in Columbus. We closed
screens 1 thru 5 and have to reopen screens 1 & 2 April 2nd for clash of the
titans.
screens 1 thru 5 and have to reopen screens 1 & 2 April 2nd for clash of the
titans.
Friday, March 5, 2010
Columbus
I am in Columbus waiting for the renovation to start. The
project has been squeezed down to 61 days. We have to
wait until 3/12/10 to start, Alice in Wonderland starts
today and it is supposed to sell a lot of tickets, so we wait
an extra week. Columbus temp 36/22.
project has been squeezed down to 61 days. We have to
wait until 3/12/10 to start, Alice in Wonderland starts
today and it is supposed to sell a lot of tickets, so we wait
an extra week. Columbus temp 36/22.