We are 60% complete with the 10 screen stadium seat renovation
in Columbus Ohio. Houses 1-4 are complete, house 5 this week &
houses 7,9 & 10 have been demo-ed, framed and are ready for
concrete. This will be a busy few weeks, Ironman 2 opens 5/7
and they want as many screens open as we can get.
Steve
Sunday, April 25, 2010
Monday, April 12, 2010
WEEK 5 COLUMBUS
After running into a few snags with the city building department
we are back in full swing. Auditoriums 1 thru 3 are finished, #4
will be complete Friday April 16th. We will close auditoriums 7,9
& 10 on the 16th as well.
Ohio weather is crazy, in the last 2 weeks we have had 70 degree
weather, 20 degree wind chill with ice and snow and 85 degrees
and humid. Spring time in the heartland yeehaw.
we are back in full swing. Auditoriums 1 thru 3 are finished, #4
will be complete Friday April 16th. We will close auditoriums 7,9
& 10 on the 16th as well.
Ohio weather is crazy, in the last 2 weeks we have had 70 degree
weather, 20 degree wind chill with ice and snow and 85 degrees
and humid. Spring time in the heartland yeehaw.