I am going home for Easter weekend, this will
be my 3rd weekend home this year. I am really
looking forward to working on the west coast.
Progress made; we have framed and poured
5 out of 8 houses, the millwork has started,
the marque is ready for the sign contractor.
The walkin coolers are being set, owner furnished
owner installed items start in May.
Wednesday, April 20, 2011
Saturday, April 16, 2011
WATERPROOFING ISSUES
We are experiencing issues waterproofing our footers on the addition. We have not had 3 days in a row without rain or snow this spring. This needs to be done so we can backfill the footers. After backfilling the footers the mason and stucco contractors have a months worth of work. I posted pictures of us putting a tent over the footers, underneath the plastic are 3 propane heaters
Wednesday, April 6, 2011
4-5-11
The finish crews start Monday 4/11/11. Painting, ceramic tile,wall carpet and handrails. The following week we have kitchen equipment and millwork. This project is winding down but not soon enough for me. 59 days until we turn it over to the owner.