WHERE I HAVE STAYED IN 2011

  • CALIFORNIA 10 DAYS
  • OHIO 3 DAYS
  • PENNSYLVANIA 105 DAYS
  • VIRGINIA 1 DAY
  • WEST VIRGINIA 1 DAY

EMAIL ADDRESS

If you need to contact me email me @ themesuperintendent@gmail.com

Total Pageviews

SINCE YOU ARE FOLLOWING MY BLOG;ARE YOU

WHERE I HAVE STAYED IN 2010

  • ALABAMA 1 NIGHT
  • CALIFORNIA (HOME) 63 DAYS
  • FLORIDA 3 DAYS
  • GEORGIA 60 DAYS
  • KENTUCKY 1 NIGHT
  • OHIO 99 DAYS
  • PENNSYLVANIA 16 DAYS
  • SOUTH CAROLINA 65 DAYS
  • TENNESSEE (OFFICE) 56 DAYS
  • VIRGINIA 1 NIGHT

Tuesday, June 7, 2011

TURNING IT OVER TO THE OWNER

We are in the process of turning the theater
over to the owner. Our contract work consists
of finishing the painting, carpet, ceramic tile
cabinet installation and punch list.
The owner venders are installing seats,screens
curtains, TV monitors and snack bar.
I will be heading home by the end of June.
Steve

Wednesday, April 20, 2011

EASTER

I am going home for Easter weekend, this will
be my 3rd weekend home this year. I am really
looking forward to working on the west coast.


Progress made; we have framed and poured
5 out of 8 houses, the millwork has started,
the marque is ready for the sign contractor.
The walkin coolers are being set, owner furnished
owner installed items start in May.

Saturday, April 16, 2011

WATERPROOFING ISSUES

We are experiencing issues waterproofing our footers on the addition. We have not had 3 days in a row without rain or snow this spring. This needs to be done so we can backfill the footers. After backfilling the footers the mason and stucco contractors have a months worth of work. I posted pictures of us putting a tent over the footers, underneath the plastic are 3 propane heaters

Wednesday, April 6, 2011

4-5-11

The finish crews start Monday 4/11/11. Painting, ceramic tile,wall carpet and handrails. The following week we have kitchen equipment and millwork. This project is winding down but not soon enough for me. 59 days until we turn it over to the owner.

Wednesday, March 23, 2011

MOTHER NATURE

I started at 5am this morning and as I was
making coffee it started snowing. The
weather in Pa. is like a ping pong ball.
Friday it was 75 degrees and 5 days
later it is snowing. At least it is the
end of March and better weather
should be on its way.

This project has been very challenging,
from the underground seating to not
having a mezzanine. Also we have lost
12 days to ice & snow and been rained
out 15 times on the exterior work.
Fortunately our client added 3 weeks
to our schedule and we now will turn
over the project 6/3/11 to the owner.

Thursday, February 24, 2011

HALFWAY

We are now halfway thru the project. Things
are really picking up and it is almost March.
I will be happy when winter ends. It was 12
degrees @ 5am this morning.

Right now we have 12 subcontractors on site
with 60 men working. It is a small building
to have so many people and equipment moving
around the site.

Sunday, February 13, 2011

BREAK IN THE WEATHER

We are finally getting a break from
mother nature with temp's in the
50's this coming week. I will take
it after losing 9 work days to ice
and snow since Christmas.

Steel erection will be complete
on the addition this week,framing
in the bar area and houses 1 & 2
are nearly complete. The HVAC
is over 50% complete. Things
are moving along nicely.